Wauwatosa Village streetscape work slotted to begin today

This rendering shows what the Village of Wauwatosa will look like after a long-anticipated streetscaping project finishes up later this year. Construction crews are scheduled to break ground May 9 and work will continue until the end of October, weather permitting.

This rendering shows what the Village of Wauwatosa will look like after a long-anticipated streetscaping project finishes up later this year. Construction crews are scheduled to break ground May 9 and work will continue until the end of October, weather permitting. Photo By City of Wauwatosa

May 9, 2016

Work on the long-awaited streetscape project is scheduled to begin May 9 in the Village of Wauwatosa, said David Jaeckels, a construction communication liaison with the city.

In the project, construction crews will be installing 8-inch-thick concrete pavers that are designed and manufactured for roadway service throughout the area. Crews will install a number of landscaping features and will create a curbless center village plaza, he said.

The project has three phases and, Jaeckels said, throughout the project, State Street will be closed from 7 a.m. to 6 p.m. Monday through Friday, but will reopen during evenings and weekends with a one-way, westbound-only lane.

Jaeckels stressed that businesses in the Village of Wauwatosa will remain open during ongoing construction.

"You'll still be able to walk and bike to Tosa businesses," he said. Parking at a business' front door could get complicated, he said.

The Village Business Improvement District has launched a campaign to inform the public that businesses will remain open throughout the process. "Keeping the Village Glowing" is the theme of the district's communication program to let the community know that businesses will remain open during streetscaping construction.

According to the Village BID's website, Harmonee Avenue will remain open during construction and eastbound traffic on the Menomonee River Parkway will be able to make right turns onto that road.

Suggested parking lots include the Harmonee Bridge and Blanchard Street lots, the northwest corner of Harmonee and Wauwatosa avenues, the Lefeber building (access using Underwood Avenue, north of State Street), Hart Park Lane (accessed from 72nd Street), Hart's Mills parking lot and the fire station lot, according to the Village BID's website.

The project is scheduled to reach substantial completion by the end of October, weather permitting.

Commenting Policy

We welcome reader discussion but strive to keep things civil. Please see our discussion guidelines and terms of use for more information. If you see a comment that violates our guidelines, please flag it for review. If you have any other issues with our commenting system, please let us know.

Suburban News Roundup

E-mail Newsletter

Your link to the biggest stories in the suburbs delivered Thursday mornings.


Enter your e-mail address above and click "Sign Up Now!" to begin receiving your e-mail newsletter
Get the Newsletter!

Login or Register to manage all your newsletter preferences.

Advertisement

Local Crime Map

CONNECT    

Advertisement

Latest Photo Galleries